BEFORE SCHEDULING AN INSPECTION

  • Please ensure your request is made by 2:00 pm on the business day before the inspection is required.
  • Refer to your Inspection Checklist and ensure that required documents are submitted to the by 2:00 pm one business day prior to the inspection date.
  • Inspections must be requested by the owner or agent
  • All work being inspected must be complete and ready prior to inspection
  • Work must not proceed past any of the required inspections listed without prior authorization
  • The street address and Building Permit card must be posted in a visible location on site
  • The approved Building Permit drawings and all prior inspection notices must be on site for all inspection

 

Any omitted information may result in an inspection not being scheduled and delay in construction.