Required Inspections for Plumbing Permits

  1. Rough Under Slab D.W.V. / Water Pipe / Water Service:  All underground piping must be tested, inspected and approved before slab preparation and pour may continue.
  2. Rough Above Slab D.W.V. / Water Pipe: All above slab piping must be tested, inspected and approved before proceeding with bathtub inspection.
  3. Bathtubs, Showers and P-Traps: All bathtubs and showers to be under test, secured to framing, and have p-traps connected to the drainage system.
  4. Final Plumbing Inspection: All fixtures and system components to be installed, cleaned and fully operational.
     

This is not an exhaustive listing of all bylaw and building code requirements. Additional information may be requested during the building permit processing.