Required Inspections for Hydronic Heating Permits

  1. Radiant Floor Panel Inspection: All in-slab piping must be inspected and approved before slab preparation and pour may continue (radiant systems).
  2. Baseboard Rough Piping Inspection: All baseboard piping loops above and below slab must be inspected and approved before proceeding (baseboard systems).
  3. Final Hydronic Heating Inspection: All appliances and system components to be installed, cleaned and fully operational as per designer's criteria. (A copy of Certification of Heating Systems form required to be on site for final inspection).
     

This is not an exhaustive listing of all R.H.W.H.A. Hydronic Guidelines and building code requirements. Additional information may be requested during the building permit processing.