Complete
During the scheduled maintenance closure of the Aquatic Centre, March 31 - April 10, the following work was completed:
- Comprehensive inspection of all four pool basins: Leisure Pool, Lap Pool, Family Hot Tub, and Adult Hot Tub.
- Inspection and cleaning beneath the movable floor in the Lap Pool.
- Detailed inspection of pool bulkheads.
- Thorough inspection and deep cleaning of gutter systems.
- Evaluation and maintenance of water features.
- Extensive tile repairs and grouting in pool basins and surrounding deck areas.
- Inspection of all bottom grates for safety and integrity.
- Full inspection of mechanical systems, including pumps, drum filters, and filtration units.
- Inspection and maintenance of sodium hypochlorite tanks and chemical feed lines.
- Cleaning and inspection of surge tanks.
- Maintenance work in the sauna and steam room, including sauna heater exchange and servicing of steam generators.
- Maintenance of stainless steel fixtures throughout the facility.
- Maintenance of on-deck showers (note: replacement system scheduled for delivery in approximately 12-15 weeks).
- General maintenance and servicing of locker units, changing room stalls, and showers.
In-progress
The following items remain in-progress or are being considered for future implementation.
- Lap Pool Maintenance: inspection, cleaning and repairs are on schedule for completion, and to reopen the Lap Pool April 23.
- Turnstiles: There is an ongoing issue with the current model of turnstiles across all current locations, rendering them non-functional at this time. We are actively working with the manufacturer to identify a suitable solution.
- Universal Change Area Glass Panel: Temporary coloured panel installed to replace broken glass until the clear glass panel arrives.
- Pool Deck Showers: A new shower system has been ordered, with delivery anticipated in 12-15 weeks. A temporary solution has been implemented by welding one of the shower handles in place so one shower is functional.
- Shoe Rack in the Universal Change Area: Scheduled for delivery in approximately 8 weeks.
- Lockers with Missing Keys: Due to a significant percentage (over 50%) of locker keys not being returned after use, we are evaluating the possible transition to a coin-return locker or free punch code system. This change is intended to ensure locker availability for facility users.
- Change Area Benches: The addition of benches in the change rooms is currently under consideration. Due to limited walkway space and budget constraints, a feasibility assessment is being conducted to identify options that balance user convenience with infrastructure constraints and cost implications.