Braid Street Water Main Replacement Project

Construction alerts

Signage and flaggers will be in place to help navigate people through a given area of work.

Project Task

Location

Duration

Impact

Watermain tie-ins and service change overs Braid Street from Canfor to Brunette May 13 to May 17 Temporary water service disruptions.
Single-lane traffic in each direction.
CN & BNSF Rail Trenchless Rail Crossing Braid St at the CN & BNSF Rail Crossing

Approx 1 month starting April 7

Night Work – Single lane Alternating Traffic

Two lanes of traffic during the day with closures for pits

Install Fibre Boxes, curb and sidewalk prep. Braid St, from Canfor to Vulcan Intermittent work Curb Lane Closures maintaining one lane of traffic in each direction

Project Background

Starting February 2019 until approximately mid-May, the City of New Westminster's contractor, Complete Utility Contractors Ltd., will be replacing a water main on Braid Street from Brunette Avenue to Canfor Avenue.

The existing water main has reached the end of its life and requires replacement in order to maintain the city’s water service into the Braid Industrial Park for both domestic use and fire protection.

The water main replacement is occurring prior to the final phase of the multi-use path construction due to pending railway approvals. The multi-use path construction is anticipated to occur in spring 2019 following the water main work but is provisional to railway approval.

Impacts

The impacts associated with the water main replacement are as follows:

  • Traffic- The contractor will endeavor to maintain vehicle traffic in each direction during construction; however, delays can be expected.
  • Driveways- At various stages of the work, access to driveways may be temporarily interrupted. The contractor will coordinate any anticipated interruptions with individual properties in advance to minimize inconveniences.
  • Parking - On-street parking will be temporarily unavailable in the work area during construction.

Project Contacts

Hooman Hedayatnassab | Project Engineer | | 604-515-3778

Adam Matheos | Project Manager | | 778-241-5792