Ryall Park Tennis Court Rehabilitation

Project updates

Task Duration Impact
Site preparation for asphalt pavement (weather dependent) Saturday March 23, 2019 Minor noise and dust due to machinery and grader.
Drainage system adjacent to the playground March 21 - March 31, 2019 Minor noise and visual disturbance, such as temporary fencing.


Background

The City of New Westminster Engineering Department will be rehabilitating the Ryall Park tennis courts. The work will include addressing settling ground conditions, resurfacing the court, new nets and new fencing. The new courts will accommodate tennis and pickleball and make for a more enjoyable recreational experience.

The work will begin January 21, 2019 and be completed sometime in April. During this time, the courts will be unavailable. Pedestrian and cyclist access will be maintained around the site. No major impacts are expected to occur for vehicle traffic.

Project Contact

If there are concerns regarding this project please contact Amir Aminpour | Engineering Project Manager | | 604-515-3796