Queensborough

Ewen Avenue

Project Task

Location

Duration

Impact

Ditch Excavation, Storm Installation

Ewen Ave (Boundary to Gifford)

Ewen Ave (Boundary - Phillips)

April 23rd - April 30th Day time road closure along Ewen Avenue between Boundary and Gifford. Detours in place. On street parking impacts. Single lane alternating traffic through construction area. Buses will be given priority. Access to affected lots will be reinstated by end of day. Full closure (24hr/day) of Boundary to Phillips. No access through this zone.
Metro Vancouver Water Main Maintenance Work Ewen Avenue at Boundary Road, Phillips Street and Jardine Street March 9th - mid April

Single lane, alternating traffic will generally be maintained on Ewen Avenue intersections at Boundary Road, Phillips Street and Jardine Street, with occasional closures. MV Crews will maintain pedestrian access on at least one side of the road at all times. Traffic control personnel will be on-site to assist pedestrian crossing.

Metro Vancouver Water Main Ewen Avenue and Boundary Road Day shift (7:00 am — 3:30 pm) and an evening shift (3:30 pm — 12:00 am) from April 12 to 30, 2018. Metro Vancouver crews will be granted a temporary noise bylaw exemption permit.
Metro Vancouver has encountered unexpected utility conflicts during construction which have resulted in construction delays and changes to the water main design. In order to complete water main construction on schedule, Metro Vancouver crews will work day shifts (7:00 AM — 3:30 PM) and may periodically work evening shifts (3:30 PM — 12:00 AM) for roughly one month.To further minimize disruption they will use low noise equipment wherever possible.

For more information, please visit www.newwestcity.ca/ewenavenue