Front Street Closure (e. columbia St to Begbie St)
Effective the week of June 17th
Please be advised that starting the week of June 17, we will implement a six-month full closure of Front Street between Begbie Street and E. Columbia Street. Front Street Mews will remain open.
This closure is required for crews to perform drainage work, install steel girders and build the new bridge deck across Front Street between the bridge foundation south of Columbia Street and the in-river foundation near the New Westminster shoreline.
While this full closure is in effect, drivers will be detoured to Columbia Street. Trucks will continue to use official truck routes (including observing applicable time restrictions). All traffic pattern changes and detours will be well signed, and traffic control personnel will be on site to direct traffic as required.
For more information, please visit the Pattullo Bridge Replacement website.