2025 Queensborough Shoreline Rehabilitation Project - Location 2
PROJECT UPDATE
April 21, 2026
We are pleased to announce that the shoreline rehabilitation work at Location 2 has reached substantial completion. All identified construction deficiencies have been addressed, and the site has now transitioned into the final phase of the project.
Vegetation Establishment Period
The project is currently in the vegetation establishment period. This phase is essential for the long-term health of the shoreline, allowing new plantings and stabilizing greenery to take root. During this time, our teams will monitor the site to ensure the natural elements are thriving and providing the intended erosion protection and habitat support.
Project Timeline
- January – February: Completion of major civil and structural dyke works.
- February 28: Target date for substantial completion of civil works.
- Spring 2026: Final mobilization for site reclamation and seasonal planting.
What's Next
Total Completion
We remain on target to achieve Total Completion by the end of May.
A Note to Residents: As the new vegetation is still in a delicate stage, we kindly ask for your cooperation in keeping off the newly planted areas to ensure the restoration is successful.
Thank you for your ongoing support and patience as we work to enhance and protect the Queensborough Shoreline.
PROJECT DETAILS
Construction of Location 2 of the Queensborough Shoreline Rehabilitation is scheduled to begin in October 2025, with final completion expected in Winter 2026. This phase builds on the successful stabilization works completed in Location 1 and continues the City’s commitment to enhancing shoreline resilience along the Queensborough foreshore.
The Queensborough Shoreline Rehabilitation Project focuses on rebuilding and reinforcing a section of the dyke to enhance its structural stability and resilience. The project involves the removal of invasive plant species, unsuitable soils, and outdated materials, followed by the import of structural fills and rock to strengthen the shoreline. These improvements are critical for protecting the dyke against erosion and ensuring its long-term reliability for flood prevention.
In addition to the structural enhancements, the project includes a comprehensive re-vegetation plan. Native and non-invasive plant species will be introduced to restore the natural environment, enhance the ecological health of the shoreline, and improve the visual appeal of the area. This rehabilitation effort reflects the City’s commitment to sustainable infrastructure and environmental stewardship.
Construction of Location 1 was completed in July 2025. The work included removing unstable timber and debris, reshaping the slope, placing geotextile and protective rock armor, and implementing native shoreline plantings. These measures have strengthened the dyke, improved habitat function, and enhanced visual quality along the waterfront.


Before After
Traffic Impacts
Duration: October 2025 - Winter 2026
Hours of Work: 7am to 7pm Monday to Friday
Night work as required for tidal access
During construction of Location 2, residents and visitors can expect:
- Equipment access and activity along the shoreline
- Minimal noise and dust as heavy machinery stabilizes the slope
Construction sequencing will be designed to minimize impacts, and the project team will monitor environmental conditions closely. Thank you for your cooperation and understanding as we complete these vital works.

Contact
For more information please contact Erika Pollmuller, AScT Senior Engineering Technologist
