Roadworks & Construction Projects
Click on the map below, then select a coloured line for more details about the project.

View in web app
Annacis Water Main North – New Westminster Section
Metro Vancouver Project - Spring 2026 to Spring 2028Metro Vancouver is constructing the Annacis Water Main North in Burnaby and New Westminster to increase the delivery of high-quality drinking water to growing communities south of the Fraser River. The new water main is approximately three kilometres long and 1.8 metres in diameter. It will run between 12th Avenue in Burnaby, and Auckland Street in New Westminster.
Work will begin with the New Westminster Section, which extends from 10th Avenue to Auckland Street. The New Westminster Section is two kilometres long and will take approximately two years to complete. Construction will take place mainly along 11th Street and 13th Street, between Auckland Street and 10th Avenue.
Contact
Community Liaison: 604-432-6200 (Monday to Friday from 8:00 am to 4:30 pm)
After Hours Emergency: 604-451-6610
Project details and latest updates can be found at: metrovancouver.org/services/water/annacis-water-main-north-new-westminster-section
Capital Paving - Various Locations
Ongoing through Summer 2026PROJECT DETAILS
Duration
Ongoing through Summer 2026Hours of Work
Monday - Friday: 7:00am - 7:00pm
Saturday: 9:00am - 6:00pmIMPACTED ROADS:
Check back for updates.
COMPLETED ROADS:
- Louellen Street - Third Ave to Fourth Ave
- Blackberry Drive
- Garfield Street
- Jamieson Court - Richmond St west to the cul de sac
- Tenth Avenue - Twelfth St to Tenth St
- Twelfth Street - Tenth Ave to Edinburgh St
- Cumberland Street - Richmond St to East Columbia St.
- Richmond Street
- East Columbia Street
- Quayside Dr and Reliance Ct Pedestrian Crossing Upgrade
- Eight Avenue - 22nd St to 20th StQuayside Drive - BC Parkway to K de K Court
- Quayside Drive - K de K Court to 10th Street
CONTACT
For more information, please contact Peter Tsoutsouras, Project Manager, at 604-636-4340 or .
Cumberland Street Rail Crossing Upgrades
Anticipated completion: AugustProject Information
The City of New Westminster has contracted Winvan Paving to complete the upgrades at the Cumberland Rail Crossing and the work is set to start September 17, 2025. The project includes upgrading the sidewalk facility between the Central Valley Greenway (West side of East Columbia) and the Brunette Fraser Regional Greenway (Sapperton Landing Park) from a 2 metre wide sidewalk to a 3.0 metre wide multi-use path (MUP). The project is anticipated to be completed in August.

Traffic Impacts
Access to and from the Sapperton Landing Pump Station and Park will be experience intermittent disruption during construction. Mitigation measures include a pedestrian and cyclist detour during sidewalk ramp closures and traffic control personnel assistance. The contractor is scheduling work activities to minimize disruptions as much as practicable.
Travel in both directions on East Columbia will be impacted during installation of the new curbs, crossings and associated let-downs. Lane closures may be in effect during working hours. Expect delays.
Hours of Work:
7:00 am to 4:00 pmContact
For any questions, please contact Garey Carlson, project manager, at 604-636-4316 or
For more information on this project, please visit Columbia St Whistle Cessation.
East Sixth Avenue Traffic Safety Improvements
Anticipated construction dates: February - August 2026Project Details
The City of New Westminster will be undertaking transportation upgrades along East Sixth Avenue between McBride Boulevard and Cumberland Street to enhance safety and accessibility for people walking, cycling, taking transit, and driving. These improvements will support improved access to the təməsew̓txʷ Aquatic and Community Centre and were identified as a priority in the City’s Active Transportation Network Plan (ATNP), adopted by Council in 2022.
The project includes a range of safety and accessibility enhancements, such as a new traffic signal at the intersection of Cumberland Street and East Sixth Avenue, intersection upgrades at Glenbrook Drive, improved access to bus stops, upgrades to the protected bike lane, new curb ramps, and enhanced street lighting. Both laneways serving təməsew̓txʷ will also be upgraded to improve pedestrian safety, along with new asphalt paving.
For more information about this project, please visit the Projects on the Go page.

Project Update
July 17, 2026
Traffic Impacts
East Sixth Avenue will continue to see single-lane traffic at times, with flaggers on site to manage traffic flow. During work at the McBride Boulevard corners, those corners may be closed with associated lane reductions. Closer to the end of the project, the road will be fully closed for a few days during final paving. A notice will go out once dates are confirmed.
TACC Entrance on Sixth Avenue Closures
The təməsew̓txʷ Aquatic and Community Centre (TACC) entrance on Sixth Avenue may be temporarily closed while construction in this area is underway. TACC patrons are encouraged to use the Seventh Avenue entrance during these closures. The Sixth Avenue entrance will always be fully open after 3 pm.
Bus Stop Notice
- The bus stop currently located in front of TACC will be temporarily relocated to in front of 479 Cumberland Street.
- The bus stop on the south side of E. Sixth Street near McBride Boulevard will remain open throughout construction.
- The bus stop on the south side of E. Sixth Street near Cumberland Street will be temporarily closed as required.
- The bus stop in front of Queen’s Park, north of E. Sixth Street near McBride Boulevard, will also be temporarily closed as required.
Remaining Work
The East Sixth Avenue Traffic Safety Improvements project is nearing completion, with substantial completion expected by mid- to late August 2026. Remaining work includes:
- Bike lane asphalt – Final curbing is being poured and grading completed ahead of asphalt paving on the multi-use pathway (MUP).
- Street light energization, Sixth Avenue and Cumberland Street – Streetlights and poles are installed; the traffic signal controller will go in over the coming weeks to activate the new lights.
- Sixth Avenue and Glenbrook Drive crosswalk – Both intersection corners will be rebuilt with new wheelchair letdowns, the median shortened, and a new, widened crosswalk installed.
- Bike lane at the Sixth Avenue Firehall – The sidewalk will be narrowed to fit a 1.5 m bike lane, and both letdowns at the adjacent intersection will be built for the MUP.
- McBride Boulevard intersection corners – Construction begins shortly; some work will occur at night.
- Lane exiting TACC to Cumberland Street – This lane will be repaved, with sections of adjacent sidewalk reconstructed.
- Full road paving on Sixth Avenue and median construction at the existing pedestrian crossing – Final curb-to-curb paving and median construction will require a full road closure for a few days.
May 19, 2026

The intersection of Cumberland Street and East Sixth Avenue will be reduced to single-lane traffic at times, with temporary no-parking restrictions in effect near the intersection. Flaggers will be on site to manage access, and work areas at the four corners will be adjusted as needed, as shown in the image above.
Project Timeline
- Construction is anticipated to take place from February 17, 2026 – August 2026.
Traffic Impacts
- Duration: February 17, 2026 to August 2026
- Hours of Work: 7:00 am – 3:00 pm, Monday to Friday; 9:00 am – 6:00 pm Saturday
- For concerns about construction hours, please contact the City’s Bylaw Enforcement Team, 604-527-4657, at the following times: Monday–Friday, 7:00am–8:00pm; Saturday, 9:00 am–6:00pm
- The project will begin at the intersection of Cumberland Street and East Sixth Avenue and will proceed west to the intersection of East Sixth Avenue and McBride Boulevard. Expect delays at the intersection of Cumberland Street and East Sixth Avenue while a new traffic signal is installed
- Bus stops on E Sixth Avenue might be temporarily closed / relocated depending on the stage of the construction, we provide further update when more information become available.
- Access Concerns: If you have any ongoing or specific access concerns related to the work, please notify us immediately so we can address them before crews demobilize.
- Waste Collection Issues: Stratas or residents experiencing issues with waste collection should reach out directly to their designated waste collection provider to coordinate service.
Frequently Asked Questions
Contact
For more information please contact Roger Chang, Project Manager, at rchang@newwestcity.ca, or visit the Projects on the Go page.
Ewen Avenue and Carter Street Raised Crosswalk
Anticipated construction dates: July 2–14Project Information
The City of New Westminster has contracted Winvan Paving to install a raised crosswalk and curb bulge as part of the Pedestrian Crossing Improvement Program.
Construction is scheduled to take place from July 2 to July 14, 2026.
The project includes upgrading the pedestrian crossing at the intersection of Ewen Avenue and Carter Street, providing improved access to the north entrance of the Queensborough Community Centre and Queensborough Middle School.
Traffic Impacts
Access to the Queensborough Community Centre and Queensborough Middle School will be maintained, however, intermittent disruptions may occur throughout the construction period.
Traffic control measures will be in place on Ewen Avenue. Users may experience changes to traffic patterns and occasional delays during median construction and pavement marking operations.
To reduce the impact on the public, signs will be provided to direct users, and traffic control personnel will be on site to assist. The contractor will coordinate construction activities to minimize disruptions wherever possible.
Traffic in both directions on Ewen Avenue will be affected during the construction of the new curbs, concrete median, raised crosswalk, and associated curb let-downs.
Temporary lane closures may be required during working hours. All users are advised to expect delays and allow extra travel time.
Hours of Work:
7:00 am to 4:00 pmContact
For any questions, please contact Peter Tsoutsouras, project manager, at 604-636-4340 or
Front Street Parkade Rehabilitation Project
Partial parkade closure until Spring 2027Project information
The Front Street Parkade Rehabilitation project is intended to renew our aging infrastructure and to improve quality and capacity where required. The project will include concrete repairs, waterproofing membrane replacement, stair railing replacement and pedestrian walkway replacement. Noisy work will occur, including jackhammering, grinding and generator noise.The project is being done in phases to keep the parkade open for the duration of the project, with restrictions to some parking areas, traffic flow and pedestrian access.Traffic impacts
The parkade remains open for parking. Please note that there will be restrictions to some parking spaces as work progresses.The Fourth St. and Sixth St. ramps will have periodic changes to their traffic patterns or closures with signage to direct traffic.Contact
For any questions, please contact Domenic Iaci or Conlan Bergeron, Project Managers, Polycrete at 604-521-4300 orHighway 91A and Howes Street Multi-Use Pathway Project
Ministry of Transportation and Transit Project: Spring - Fall 2026Please be advised that this is a Ministry of Transportation and Transit project. We kindly ask that you direct all questions, comments, or complaints regarding construction activities or traffic management directly to the ministry. For the most current project details, official advisories, and progress photos, please visit the Government of BC website.
Project Overview:
This project will upgrade an existing pathway along the southbound side of Howes Street between Ewen Avenue and Boyd Street, replacing it with a multi-use pathway that improves connectivity and safety for pedestrians and cyclists. This new pathway contributes to a larger initiative to improve active transportation opportunities throughout Queensborough and connect the residential and commercial areas divided by the Highway 91A Queensborough Connector.
At the Boyd Street intersection the new pathway will tie-in to the upgraded Boyd Street multi-use pathway constructed by the City of New Westminster.
The project includes:
- 4 metre wide multi-use path
- New lighting
- Drainage enhancements
- Improved pedestrian and cyclist crossings
Pedestrian and cyclist access will be maintained throughout construction.
For information about this project, contact:
Pattullo / stal̕əw̓asəm Bridge Replacement Project
July 16–24: Overnight closures of the Royal Avenue on-rampProject Update
Update: July 20, 2026
July 16–24: Overnight closures of the Royal Avenue on-ramp will occur between 9 pm and 5 am for approximately one week, for crews to install concrete deck panels on the multi-use path overpass that crosses over the Royal Avenue on-ramp and Bridge Connector in New Westminster.
Drivers using the Royal Avenue on-ramp to the stal̕əw̓asəm (Riverview) Bridge can instead take Sixth Street to Sixth Avenue, and McBride Boulevard to Bridge Connector.Lane closures of Bridge Connector will also be required between 10 pm and 5 am for approximately one week. One lane in each direction will be maintained, except during 20-minute intermittent periods, when single-lane alternating traffic will be in place.Please visit the project website for more information.
Multi-use path (MUP) opened June 1: The multi-use path (MUP) on the east side of the stal̕əw̓asəm Bridge opened to pedestrians and cyclists in both directions on the morning of Monday, June 1.
Additional information for pedestrians and cyclists can be found at pattullobridgereplacement.ca/active-transportation
February 13, 2026
After 89 years of service, the Pattullo Bridge is now permanently closed to all vehicle traffic.
All four lanes on the new stal̕əw̓asəm Bridge opened to traffic beginning on February 14, 2026.
Removal of the Pattullo Bridge is scheduled to begin in late February with the removal of a section of the Pattullo Bridge over Columbia Street and the construction of the new Columbia on-ramp and E. Columbia multi-use path overpass. This work requires the following traffic changes:
- Closure of the existing Columbia Street loop-ramp to the Pattullo Bridge – starting Saturday, February 14.
- Columbia Street between 6th and Elliot will remain open for local traffic and access to all businesses on Columbia Street and Front Street Mews will be maintained at all times.
The Pattullo Bridge is a key connection between the communities of Surrey and New Westminster. The new toll-free four-lane bridge will provide important improvements for everyone using the bridge, including people who are driving, cycling or walking, as well as communities on either side of the bridge.
Click to view latest traffic impacts
To learn more about his project, as well as upcoming construction activity, please visit: www.pattullobridgereplacement.ca
For construction information or concerns, please call the 24/7 Construction Information Line at 1-844-815-6149.
For general project information, please email the project team at: , or call 844-815-6149.
Rotary Crosstown Greenway (5th - 8th Street)
Anticipated completion: June 2026Project Details
The City of New Westminster is enhancing the Rotary Crosstown Greenway along Seventh Avenue between Fifth and Eighth Streets to provide a safer, more comfortable, and attractive route for people of all ages and abilities to walk, bike, and roll.
As part of this work, the corridor will be upgraded with protected bike lanes, improved pedestrian crossings, new landscaping, and refreshed road surfaces. A mid-block raised crosswalk between Sixth and Eighth Streets will increase safety and visibility for pedestrians. The design reflects feedback gathered through public engagement and supports the City's broader goals for active transportation and accessibility.
Construction is now underway and will be completed in phases to minimize disruption.

Project Update
June 8, 2026
We are nearing completion of the final phase of construction on the Rotary Crosstown Greenway. This work includes final touch ups of the concrete medians, signage installation, and line painting.
Weather Delay & Revised Schedule
Due to weather restrictions last week, our line painting has been delayed. Work will now progress this week based on the revised dates below. Residents should expect significant activity and temporary changes to traffic flow during these times.
Traffic Impacts
Location / Scope
Estimated Dates
Night Work
Line painting and road marking
Due to unfavorable weather last week, there has been a delay in the completion of the line markings. There is one night of work activity remaining, and the contractor is on standby to complete work at the earliest favorable weather window.
One night only between June 9 to 11
Local Traffic
For the duration of these works, local access will be maintained for all residents living within the construction zone. While there may be temporary interruptions to traffic and pedestrian flow, please follow the directions of traffic control personnel to safely reach your property.
Waste Collection Notice
Strata's and buildings with private waste removal are advised to contact their collection providers directly. Please ensure your pickup is scheduled outside of the full closure dates to avoid service interruptions.
Contact
For more information please contact Erika Pollmuller, Project Manager, at , or visit the Projects on the Go page.
Seventh Street - ATNP Year 1 Implementation
Anticipated completion: Spring 2026Project Details
The City of New Westminster is upgrading Seventh Street between Queens Avenue and Sixth Avenue as part of Year 1 implementation of the All Ages and Abilities (AAA) Active Transportation Network Plan. This project is designed to improve safety, comfort, and accessibility for people walking, cycling, and rolling through the Uptown neighbourhood.
The improvements will include:
- New protected bike lanes
- Upgraded pedestrian infrastructure
- Enhanced street features and traffic calming
- A permanent conversion of Seventh Street to a one-way northbound configuration from Queens Ave to Fifth Ave.
Construction will be completed in phases to minimize disruption to residents and businesses.
.jpg)
Project Update
We are excited to announce that the Seventh Street project has officially reached total completion. All outstanding work, including the final spring touches and minor repairs identified during our inspections, has been successfully finished.
The corridor is now fully operational in its final design. As we settle into this permanent layout, we want to ensure everything is working exactly as intended:
Users are our Best Inspectors: While our teams have conducted thorough reviews, those who use the street daily often spot things we might miss.
If you notice a deficiency or something that looks "off," users are encouraged to report through our Click-Fix system. Your real-time feedback helps us keep the street safe and functional.
What's Next: Traffic Study & Assessment
With total performance achieved, the Transportation Department is now moving into the formal evaluation phase. We will be launching a comprehensive traffic study to monitor the project’s performance in its completed state.
This study will analyze:
- Design Impact: Measuring how the new infrastructure has improved safety and accessibility for all road users.
- Operational Flow: Evaluating how current traffic and parking patterns compare to our initial projections.
- Future Adjustments: Identifying if any further refinements or minor adjustments are necessary based on real-world data and community feedback.
Thank you for your patience and cooperation throughout this first year of activation!
Contact
For more information please contact Erika Pollmuler, project manager, at or visit the Projects on the Go page.
Seventh Avenue West Corridor - BC Parkway to Tenth Street
Anticipated completion: May 2026Project Details
The City of New Westminster is enhancing the Rotary Crosstown Greenway along Seventh Avenue between the BC Parkway and Tenth Street to provide a safer, more comfortable, and attractive route for people of all ages and abilities to walk, bike, and roll.
This project includes refreshed line painting, protected intersections for cyclists, new speed cushions to calm traffic, and improved street lighting.
Project Timeline
Project Update March 2026
- Signage installation, paving and road line marking work is still outstanding and will be completed once weather conditions are dry and warm enough.
- The project is currently scheduled to be completed in May 2026
Contact
For more information please contact Peter Tsoutsouras at ptsoutsouras@newwestcity.ca, or visit the Projects on the Go page.
Sewermain Rehabilitation Program
Overnight Partial Road Closures - July 8project Update
June 26, 2026
As part of the Sewer Rehabilitation Program, nighttime works is scheduled on several streets. By conducting this work at night, we aim to minimize construction impact on the community during peak hours while prioritizing public health and safety.
Night Work Details:
- Contractor: Insituform Technologies
- Date (tentative): July 8, 2026
- Work hours: 6:00 PM – 12:00 AM
- Scope: Sewermain rehabilitation
- Emergency contact: Bryan Smith, Insituform Technologies, 204-557-1798
- Locations:
- Regina Street (between Third Street and Second Street)
- Sixth Street (between Clarkson Street and Columbia Street)
A temporary partial road closure will be in effect. During this period, expect the use of machinery, backup alarms, generators, pumps, lighting, and vacuum trucks.
A comprehensive Traffic Management Plan has been developed to ensure the safe and efficient movement of traffic, pedestrians, and cyclists. To mitigate potential disruptions, advance notifications will be sent to neighbouring properties and businesses.
A dedicated contact phone number will also be provided, allowing residents to report any issues or concerns that may arise during the night work. Our team is committed to minimizing noise levels and ensuring that all work is carried out with the least possible disturbance to the community.
If you have any questions or concerns during the work, please contact Bryan Smith at 204-557-1798. Every effort will be made to minimize noise and disruption to the community.
West End Sewer Separation and Watermain Replacement Project
Temporary closures and parking disruptions for paving August–November 2026project Update
July 9, 2026
Starting in August, the second phase of paving work will begin as part restoration works for the West End Sewer Separation and Watermain Replacement Program in New Westminster.
Construction will include roadway milling, asphalt paving and pavement marking restoration, where required with the goal of improving road conditions and neighbourhood safety.
- Dates: August 2026 to November 2026 (weather dependent)
- Hours of Work: Monday - Friday: 7:00 am - 7:00 pm, Saturdays: 9:00 am - 6:00 pm
- Impacted Roads: View map
-
18th Street Catchment - 10th Ave to 5th Ave
-
20th Street Catchment – area enclosed by 20th Street to 16th Street and London Street to Fifth Avenue
-
6th Avenue – from 13th Street to 14th Street
-
Some parking disruptions will occur on impacted roads to accommodate the necessary staging areas. We respectfully ask that residents and visitors not park in these areas.
Expect temporary road closures, traffic delays and sidewalk closures during construction. Alternate access points will be provided, and advance notice will be given.
May 11, 2026
Final paving work will begin in late May on 16th Street and 6th Avenue. Construction will include roadway milling, asphalt paving and pavement marking restoration where required with the goal of improving road conditions and neighbourhood safety.
- Dates: May 2026 - August 2026 (weather dependent)
- Hours of Work: Monday - Friday: 7:00 am - 7:00 pm, Saturdays: 9:00 am - 6:00 pm
- Impacted Roads: View map
- 16th Street – 10th Avenue to 6th Avenue
- 6th Avenue – 18th Street to 20th Street
- 8th Avenue – 20th Street to 14th Street
- London St, Dublin St, Hamilton St, and Nanaimo St – 16th Street to 14th Street
Some parking disruptions will occur on impacted roads to accommodate the necessary staging areas. We respectfully ask that residents and visitors not park in these areas.
Expect temporary road closures, traffic delays and sidewalk closures during construction. Alternate access points will be provided, and advance notice will be given.
Following paving, crews will undertake site restoration, including general clean-up, to return the area to a safe and fully functional condition.
PROJECT DETAILS
The project will include sewer separation work, installing green infrastructure (rain gardens), and replacing water mains that are at the end of their service life and due for replacement. The water main and sanitary sewer replacement program is intended to renew our aging infrastructure and to improve quality and capacity where required.
Duration
April 2024 to Spring 2027 (weather dependent)
Hours of Work
Monday - Friday: 7:00 am - 7:00 pm
Saturdays: 9:00 am - 6:00 pmImpacted Roads
Sixth Avenue - 20th Street to 18th Street
Duration: Fall 2023 - Summer 202516th Street - Tenth Avenue to Fifth Avenue
Duration: Spring 2024 - Fall 202518th Street - Tenth Avenue to Sixth Avenue
Duration: Fall 2024 - Spring 202620th Street - Tenth Avenue to Sixth Avenue
Duration: Winter 2026 - Spring 2027For more information on this project, please contact Amir Aminpour, Project Manager, at 604-515-3796 or or
2025 Queensborough Shoreline Rehabilitation Project - Location 2
Anticipated completion: Spring 2026PROJECT UPDATE
April 21, 2026
We are pleased to announce that the shoreline rehabilitation work at Location 2 has reached substantial completion. All identified construction deficiencies have been addressed, and the site has now transitioned into the final phase of the project.
Vegetation Establishment Period
The project is currently in the vegetation establishment period. This phase is essential for the long-term health of the shoreline, allowing new plantings and stabilizing greenery to take root. During this time, our teams will monitor the site to ensure the natural elements are thriving and providing the intended erosion protection and habitat support.
Project Timeline
- January – February: Completion of major civil and structural dyke works.
- February 28: Target date for substantial completion of civil works.
- Spring 2026: Final mobilization for site reclamation and seasonal planting.
What's Next
Total Completion
We remain on target to achieve Total Completion by the end of May.
A Note to Residents: As the new vegetation is still in a delicate stage, we kindly ask for your cooperation in keeping off the newly planted areas to ensure the restoration is successful.
Thank you for your ongoing support and patience as we work to enhance and protect the Queensborough Shoreline.
PROJECT DETAILS
Construction of Location 2 of the Queensborough Shoreline Rehabilitation is scheduled to begin in October 2025, with final completion expected in Winter 2026. This phase builds on the successful stabilization works completed in Location 1 and continues the City’s commitment to enhancing shoreline resilience along the Queensborough foreshore.
The Queensborough Shoreline Rehabilitation Project focuses on rebuilding and reinforcing a section of the dyke to enhance its structural stability and resilience. The project involves the removal of invasive plant species, unsuitable soils, and outdated materials, followed by the import of structural fills and rock to strengthen the shoreline. These improvements are critical for protecting the dyke against erosion and ensuring its long-term reliability for flood prevention.
In addition to the structural enhancements, the project includes a comprehensive re-vegetation plan. Native and non-invasive plant species will be introduced to restore the natural environment, enhance the ecological health of the shoreline, and improve the visual appeal of the area. This rehabilitation effort reflects the City’s commitment to sustainable infrastructure and environmental stewardship.
Construction of Location 1 was completed in July 2025. The work included removing unstable timber and debris, reshaping the slope, placing geotextile and protective rock armor, and implementing native shoreline plantings. These measures have strengthened the dyke, improved habitat function, and enhanced visual quality along the waterfront.


Before After
Traffic Impacts
Duration: October 2025 - Winter 2026
Hours of Work: 7am to 7pm Monday to Friday
Night work as required for tidal accessDuring construction of Location 2, residents and visitors can expect:
- Equipment access and activity along the shoreline
- Minimal noise and dust as heavy machinery stabilizes the slope
Construction sequencing will be designed to minimize impacts, and the project team will monitor environmental conditions closely. Thank you for your cooperation and understanding as we complete these vital works.

Contact
For more information please contact Erika Pollmuller, AScT Senior Engineering Technologist
Queensborough Bridge Renewal Project
Ministry of Transportation and Infrastructure Project - Fall 2027Please be advised that this is a Ministry of Transportation and Transit project. We kindly ask that you direct all questions, comments, or complaints regarding construction activities or traffic management directly to the ministry. For the most current project details, official advisories, and progress photos, please visit the ministry’s website at the following link: www2.gov.bc.ca/gov/content/transportation-projects/other-transportation-projects/queensboroughbridge
The Queensborough Bridge Renewal Project has officially entered its active construction phase this spring. Crews have begun critical work to enhance the safety, reliability, and structural longevity of this essential Highway 91A crossing. This comprehensive rehabilitation includes resurfacing the bridge deck with a high-performance concrete overlay, replacing aging deck joints, and upgrading the drainage system. These improvements are vital for maintaining a structure that serves nearly 88,000 vehicles daily, ensuring it remains a robust link between New Westminster and Lulu Island for decades to come.
To minimize disruptions for commuters, the majority of the work is being performed during nighttime hours. Motorists should expect lane closures between 9:30 pm and 5:00 am on weekdays, and until 9:00 am on weekends. During these windows, traffic will be reduced to one lane in each direction, and a 3.5-meter width restriction will be in effect for oversized vehicles. While these nightly patterns will continue through the summer before pausing for the winter season in November, pedestrian and cyclist access will remain open throughout the project. We appreciate the community’s patience as we work toward a projected completion in fall 2027.
RCH Redevelopment Project
Overnight work June 12 – July 24Update: June 11, 2026
Overnight work: The project will have extended work hours from 8:00 pm to 7:00 am Monday to Friday between June 12 and July 24, 2026 (excluding Saturdays, Sundays and statutory holidays) to undertake overnight work near Keary Street.
For any after hours issues on site please call 236-332-2370.Phase two was completed in May 2026 with the opening of the Jim Pattison Acute Care Tower.
Phase three of the redevelopment project will upgrade and expand areas in the existing Health Care Centre and Columbia Tower to support the beds and services added in phase two. Phase three is projected to continue until 2029.
Standard construction hours are Monday to Friday, 7:00 am to 8:00 pm (except holidays) and Saturday, 9:00 am - 6:00 pm.