Housing Supply Act & Target Order

Target Order

In July 2024, the Province issued a Housing Target Order for New Westminster. We are required to build 4,432 net new units over five years from August 1, 2024 to July 31, 2029. The Order is one of the legislative changes brought in by the Province with the goal of addressing the housing crisis.

The target is 75% of the total estimated housing need based on the Province's methodology. The Province encourages the City to try to meet 100% of the total estimated housing need (5,909 net new units).

In addition to the target, the Province has issued guidelines for how those units should be distributed based on number of bedrooms, rental, below market, and supportive units. 

Units by Size

Unit CategoryGuideline
Studio/One Bedroom*2,423
Two Bedroom832
Three or More Bedrooms1,176

*(1 Bedroom Minimum 909)

Units by Tenure

Unit CategoryGuideline
Rental2,298
Owned2,133
Three or More Bedrooms1,176

Rental Units by Affordability

Unit CategoryGuideline
Market1,109
Below-Market1,189
Three or More Bedrooms1,176

Supportive Rental Units

Unit CategoryGuideline
With On-site Supports63
Below-Market1,189
Three or More Bedrooms1,176

Progress will be evaluated based on the number of net new occupied units and actions we are taking to increase housing supply.

Progress Toward Meeting Housing Target

The City is required to report on progress made and actions taken toward meeting Housing Targets. An interim progress report was required after six months and one year. Subsequent reporting is required annually until 2029.

During the Year One reporting period, from August 1, 2024 to July 31, 2025, there have been 1,175 net new housing units completed in the city. This exceeds the Year One target by 519 units, which will count toward the City's Year Two cumulative housing target of 1,388 units. To meet the City's Year Two target, an additional 213 net new units are required to be completed by July 31, 2026.

While we have met our Year One housing target, this achievement is a result of long-term efforts initiated long before the Housing Target Order took effect. The City will continue to strive to meet the targets; however, the completion of new units relies on developer timelines, which are in turn largely driven by market conditions.

The next provincial reporting deadline is July 31, 2026.