Massey Theatre Renovation Project

Project Status
In Progress
Category
Public Art and Heritage

Project Overview

The Massey Theatre Complex renovation project will see significant upgrades made to the existing facility to improve energy efficiency, accessibility, and the exterior envelope. The City of New Westminster's contribution of $34.1 million reflects the City's ongoing commitment to the cultural sector through strategic investment and recognizes the importance of this civic cultural asset to the local and regional arts community. Additionally, this work aligns with the strategic priorities outlined in the 2019-2024 Arts Strategy (PDF) and 2019 Theatre Strategy (PDF).

Throughout the project, the City will work alongside its operating partner, the Massey Theatre Society (MTS), to fulfill the shared vision of bringing together the opportunities, capabilities and resources of both organizations to improve the facility and its specialized functions for the enjoyment of all citizens of New Westminster.

The renovation project aims to extend the life of the Complex and provide a modernized space with improved energy efficiency and accessibility features. The Massey Theatre Complex will remain open and vibrant with plenty of performances and community activities as the upgrades progress. Updates on the phases of renovation will be provided as we move through the project.

Did you know?

We’re sharing fun facts and updates throughout the Massey Theatre Renovation. Check out the latest updates.

Construction Updates

As part of Phase 3 construction work, which includes complex and invasive upgrades to the roof, HVAC system, and building envelope, the Massey Theatre complex will be closed from July 1 to November 30, 2026. This closure is required to allow for critical work to be completed safely and efficiently, and to ensure the project remains on track.

For information on programs or performances, please visit masseytheatre.com

Phase 3 - Until Fall 2027

Phase three of facility upgrades is scheduled to take place from July 2025 to Fall 2027.

Work in 2026 to include:

  • All-gender and accessible washroom upgrades
  • Interior HVAC and room/studio finishes
  • HVAC system upgrade to all-electric air source heat pump system
  • New back-of-house utility addition including electrical distribution upgrade
  • Foundation upgrade with drainage and waterproofing
  • North elevation building envelope
  • Accessibility upgrades including new elevators, interior ramps and public washroom replacement

Work in 2027 to include:

  • Building envelope upgrades including new roofs, exterior walls, windows and doors
  • Parking lot improvements
  • Public realm upgrades including new landscaping, additional parking stalls, and electric vehicle charging stations
  • Final cleanup and project completion

Phase 2 - Winter 2025

Phase 2 is now complete and included the deconstruction of the large gymnasium wing.

Phase 1 - Fall 2024

The first phase of facility upgrades for the Massey Theatre and Complex is complete and involved relocating the incoming water service, water entry room, fire sprinkler distribution piping and fire department connection.

Image
Massey Theatre Parking Map

Frequently Asked Questions (FAQ)

Project Contact

For more information on the project, please contact Karen Campbell, Manager, Civic Buildings Capital Projects at kcampbell@newwestcity.ca