Notice of Completion

 

Title Tender Number Contractor Date of Substantial Completion
2018 Capital Pavement Program NWIT-18-04

Mainland Construction Materials ULC Dba Winvan Paving

February 14, 2019
Tipperary Park Improvements   Canadian Landscape And Civil Services Ltd April 1, 2019

Boyd Street & Derwent Way Roadway Lighting & Fibre Optic Infrastructure

NWIT-18-30 Complete Utility Contractors Ltd

April 24, 2019

 

Tenth Avenue Roadway Lighting and Fibre
Optic Infrastructure
NWIT-18-28 Complete Utility Contractors Ltd May 17, 2019