Pattullo / stal̕əw̓asəm Bridge Replacement Project
Project Update
This is Province of BC project. To learn more and see upcoming construction notices, please visit: www.pattullobridgereplacement.ca
Update: September 15, 2026
Bridge Connector lane closures: Starting the night of Monday, September 21, for approximately two nights from 10:00 pm to 5:00 am.
Royal Avenue on-ramp closures: Starting the night of Monday, September 21, for approximately three nights from 9:00 pm to 5:00 am.
Overnight left lane closures: Starting Friday, September 18, left lane closures in both directions on the stal̕əw̓asəm Bridge will be in effect for approximately two weeks for south approach realignment work.
- One lane of traffic in each direction will be maintained, and access to the multi-use path on the east side of the stal̕əw̓asəm Bridge will be maintained.
Four-month closure of the Front Street truck route starts August 31
- Front Street Mews will remain open and access to businesses in downtown New Westminster will be maintained at all times.
- Nearby residents may hear noise associated with construction activities.
- While this closure is in effect, trucks will be required to use official truck routes (which exclude Columbia Street at all hours, and Royal Avenue after 9:00 pm). Regular traffic will be detoured to Columbia Street.
For questions or concerns
For construction information or concerns, please call the 24/7 Construction Information Line at 1-844-815-6149.
For general project information, please email the project team at: , or call 844-815-6149.