Roadworks & Construction Projects
Click on the map below, then select a coloured line for more details about the project.

View in web app
Nightwork - Massey Theatre
November 7 - 10Please be advised that the Engineering Department will be issuing a Noise Bylaw Variance to Heatherbrae Builders / Fontaine Site to permit night work to accommodate underground stormwater connection work required as part of the Massey Theatre Renovation Project, located at 735 Eighth Avenue.
Due to high pedestrian and vehicle volumes during daytime hours, a portion of this work has been scheduled to occur overnight to ensure public safety and to minimize disruption to businesses and residents in the area.
Night work details:
Contractor: Heatherbrae Builders / Fontaine Site Services
Dates: November 7th – November 10th
Work hours: Continuous day and night shifts, up to 24-hr operations
Scope: Underground stormwater connection at Eighth Avenue and Massey Theatre. The impacted areas are the short road and parking spaces between Moody Park Arena and Massey Theatre, typically accessed via Eighth Avenue.

A temporary road closure will be in effect during this period, during which you can expect the use of machinery, backup alarms, generators, pumps, lighting, and vacuum trucks.Our team is committed to keeping noise levels to a minimum and completing all work with the least possible disturbance to the community.
Contact
For any questions about this project, please contact Karen Campbell, Project Manager, at .
Metro Vancouver's Regional Water Meter Upgrades - Sherbrooke Street
November 12th, 2025 to April 30th, 2026 (24/7) For more information, please visit Metro Vancouver’s websitePROJECT IMPACTS:
- Full Road Closure of Sherbrooke Street, including the north sidewalk, between Blair Avenue and Richmond Street for approximately six months.
- Pedestrians will be detoured to the south sidewalk and access to the resident’s houses fronting the project will be maintained.
- Cyclists and vehicle traffic will be detoured via the approved detour route.
- A Traffic Control Person will be on-site during construction to assist pedestrians and vehicle traffic, as needed.

CONTACT INFORMATION:
2025 Queensborough Shoreline Rehabilitation Project - Location 2
Nightwork Nov 3 to Dec 19, 2025 (weather dependent)PROJECT UPDATE
November 2025
lease be advised that the Engineering Department will be issuing a Noise Bylaw Variance to JJM Contracting to permit night work as part of the ongoing Queensborough Shoreline Rehabilitation project behind the Starlight Casino.
Due to limited low-tide windows required for in-water work, a portion of this project will be completed overnight at the lowest tides for November and December. This work is in the industrial area behind the Starlight Casino and Tree Island Industries.
Night Work Details:
- Contractor: JJM Construction
- Dates: November 3 to December 19, 2025
- Work Hours: 7:00 p.m. – 5:00 a.m.
- Scope: Reconstruction of critical dyke infrastructure in the commercial and industrial area behind the Starlight Casino.
PROJECT DETAILS
Construction of Location 2 of the Queensborough Shoreline Rehabilitation is scheduled to begin in October 2025, with final completion expected in Winter 2026. This phase builds on the successful stabilization works completed in Location 1 and continues the City’s commitment to enhancing shoreline resilience along the Queensborough foreshore.
The Queensborough Shoreline Rehabilitation Project focuses on rebuilding and reinforcing a section of the dyke to enhance its structural stability and resilience. The project involves the removal of invasive plant species, unsuitable soils, and outdated materials, followed by the import of structural fills and rock to strengthen the shoreline. These improvements are critical for protecting the dyke against erosion and ensuring its long-term reliability for flood prevention.
In addition to the structural enhancements, the project includes a comprehensive re-vegetation plan. Native and non-invasive plant species will be introduced to restore the natural environment, enhance the ecological health of the shoreline, and improve the visual appeal of the area. This rehabilitation effort reflects the City’s commitment to sustainable infrastructure and environmental stewardship.
Construction of Location 1 was completed in July 2025. The work included removing unstable timber and debris, reshaping the slope, placing geotextile and protective rock armor, and implementing native shoreline plantings. These measures have strengthened the dyke, improved habitat function, and enhanced visual quality along the waterfront.


Before After
PROJECT TIMELINE
Construction for Location 2 will begin in October 2025, with work continuing through the fall and into Winter 2026. The project is expected to take approximately 4-6 months to complete, depending on weather conditions and tidal access.
Work will be carried out in stages to limit disruption to nearby residents and protect environmental features along the shoreline.
WHAT'S NEXT?
As construction begins on Location 2, the following activities are expected in the coming weeks:
- Contractor mobilization to the site, including equipment delivery and staging
- Installation of construction fencing along the shoreline work zone for public safety
- Temporary parking restrictions in adjacent areas to accommodate machinery and materials
Regular updates will be shared as work progresses through Fall 2025 and Winter 2026.
TRAFFIC IMPACTS
Duration: October 2025 - Winter 2026
Hours of Work: 7am to 7pm Monday to Friday
Night work as required for tidal accessDuring construction of Location 2, residents and visitors can expect:
- Equipment access and activity along the shoreline
- Minimal noise and dust as heavy machinery stabilizes the slope
Construction sequencing will be designed to minimize impacts, and the project team will monitor environmental conditions closely. Thank you for your cooperation and understanding as we complete these vital works.

CONTACT
For more information please contact Erika Pollmuller, AScT Senior Engineering Technologist
Cumberland Street Rail Crossing Upgrades
September 17th for approximately 3 monthsProject Information
The City of New Westminster has contracted Winvan Paving to complete the upgrades at the Cumberland Rail Crossing and the work is set to start September 17, 2025. The project includes upgrading the sidewalk facility between the Central Valley Greenway (West side of East Columbia) and the Brunette Fraser Regional Greenway (Sapperton Landing Park) from a 2 metre wide sidewalk to a 3.0 metre wide multi-use path (MUP). The project will take approximately 3 months to complete.

Traffic Impacts
Access to and from the Sapperton Landing Pump Station and Park will be experience intermittent disruption during construction. Mitigation measures include a pedestrian and cyclist detour during sidewalk ramp closures and traffic control personnel assistance. The contractor is scheduling work activities to minimize disruptions as much as practicable.
Travel in both directions on East Columbia will be impacted during installation of the new curbs, crossings and associated let-downs. Lane closures may be in effect during working hours. Expect delays.
Hours of Work:
7:00 am to 4:00 pmContact
For any questions, please contact Garey Carlson, project manager, at 604-636-4316 or
For more information on this project, please visit Columbia St Whistle Cessation.
Uptown Plaza and Sixth Street Public Realm Improvements
September 15 through NovemberpROJECT UPDATE
September 16th update
The project is substantially complete, with the exception of trees which will be installed in October. Planting during the summer heat can stress young trees and increase the risk of failure. Deficiencies will also be addressed once the portion of construction at Sixth Street and Princess Street is complete.
September 11th update
Sixth Street @ Princess Street Construction
Project Information
- Installation of concrete curb bulge on the Princess St & Sixth St intersection Southbound
- Installation of bus shelter
-
Extending the sidewalk and replacement of sidewalk sections
-
New loading zone on the North side of Princess St / Sixth St
-
Replacement of planting trees along Sixth St
Duration
Construction will start September 15th through November
Traffic Impacts
- Sidewalk will remain open but may be restricted to 1.5m to 1.8m wide.
- Access to Princess St will remain open
- Taxi zone will be used as a temporary loading zone
Project Details
Please be advised that the City of New Westminster’s contractor, GPM CIVIL CONTRACTING, is scheduled to commence the Uptown Plaza and Sixth St Public Realm Works. The primary extents of the project are on Sixth Street, from Sixth Avenue to Belmont Street, and Belmont Plaza (located on Belmont Street between Sixth Street and midblock to Seventh Street). It will also include improvements to the west side of Sixth Street between Princess Street and Sixth Avenue.

Project Timeline
February 17th through October 2025
Hours of Work
Monday - Friday: 7am-8pm
Saturday: 9am-6pmTraffic Impacts
Temporary lane closures may be in effect during working hours. Expect delays.
We will endeavor to minimize disruption as much as possible to businesses and residents. However, as with a project of this nature, please expect some additional noise and dust during construction. If special consideration is required, please contact the City’s project manager.
Parking Map
Please see the Parking Map for available for parking locations during construction.
Contact Information
For more information please visit the Projects on the Go page, or please contact
Seventh Avenue West Corridor - BC Parkway to Tenth Street
Anticipated completion: December 2025 (weather permitting)Project Details
The City of New Westminster is enhancing the Rotary Crosstown Greenway along Seventh Avenue between the BC Parkway and Tenth Street to provide a safer, more comfortable, and attractive route for people of all ages and abilities to walk, bike, and roll.
This project includes refreshed line painting, protected intersections for cyclists, new speed cushions to calm traffic, and improved street lighting.
Project Timeline
Project Update September 2025
Crews will begin mobilizing on Monday, September 22, 2025, with work scheduled to be completed by the end of December 2025 (weather permitting). Construction will start at the intersection of Seventh Avenue and Tenth Street and progress block by block toward the BC Parkway.
What’s Next?
- Minor traffic impacts during construction.
- Local traffic will continue to have access to driveways.
- Street parking will be restricted during working hours, with “No Parking” signs posted in advance.
- Monthly updates will be posted to this webpage and shared via City social media
- Schedule adjustments may occur depending on weather and site conditions
Traffic Impacts
Duration:
September 22nd to the end of October 2025Hours of Work:
7 am to 7 pm Monday to Friday
9 am to 5 pm SaturdayDuring construction, residents and visitors can expect:
- Temporary lane closures on Seventh Avenue.
- On-street parking restrictions.
- Adjusted cycling and pedestrian routes
- Active traffic control personnel to guide road users safely.
During construction, residents and visitors can expect:
- Temporary lane closures on Seventh Avenue
- On-street parking restrictions
- Adjusted cycling and pedestrian routes
- Active traffic control personnel to guide road users safely
Expect delays, and please follow all posted signage for your safety and our crews.
Garbage and recycling services will continue as usual, and access to homes and businesses will be maintained.
We appreciate your cooperation and understanding as we deliver these important upgrades.
Contact Information
For more information please contact Peter Tsoutsouras at ptsoutsouras@newwestcity.ca, or visit the Projects on the Go page.
Capital Paving - Various Locations
Ongoing throughout the FallPROJECT DETAILS
Duration
August 11th through NovemberHours of Work
Monday - Friday: 7:00am - 7:00pm
Saturday: 9:00am - 6:00pmIMPACTED ROADS:
- Cumberland Street - Richmond St to East Columbia St
Duration: September 29 to mid-November
- Richmond Street - East Columbia St to Cumberland St
Duration:TBD
- Twelfth Street - Tenth Ave to Edinburgh St
Duration:TBD
- Tenth Avenue - Twelfth St to Tenth St
Duration:TBD
- East Columbia Street - Hoult St to Hume Park
Duration:TBD
- Quayside Drive - K de K Court to Stewardson Way
Duration:TBD
- Eighth Avenue - 22nd St to 20th St
Duration:TBD
COMPLETED ROADS:
- Louellen Street - Third Ave to Fourth Ave
- Blackberry Drive
- Garfield Street
- Jamieson Court - Richmond St west to the cul de sac
CONTACT
For more information, please contact Peter Tsoutsouras, Project Manager, at 604-636-4340 or .
- Cumberland Street - Richmond St to East Columbia St
Seventh Street - ATNP Year 1 Implementation
September 22 to December 2025Project Details
The City of New Westminster is upgrading Seventh Street between Queens Avenue and Sixth Avenue as part of Year 1 implementation of the All Ages and Abilities (AAA) Active Transportation Network Plan. This project is designed to improve safety, comfort, and accessibility for people walking, cycling, and rolling through the Uptown neighbourhood.
The improvements will include:
- New protected bike lanes
- Upgraded pedestrian infrastructure
- Enhanced street features and traffic calming
- A permanent conversion of Seventh Street to a one-way northbound configuration from Queens Ave to Fifth Ave.
Construction will be completed in phases to minimize disruption to residents and businesses.
.jpg)
Project Timeline
Project Update November 10, 2025
Construction is continuing through November, with crews now mobilizing to the intersection of Seventh Street and Belmont Street to complete pedestrian and traffic safety improvements. This work will include the removal and replacement of sidewalks, curb letdowns, and pavement to allow for regrading and improved accessibility. Please follow all posted signage and directions from traffic control personnel when travelling through the area.
Line painting and cycling lanes have now been completed from Agnes Street to Belmont Street, and the new one-way traffic pattern is active. Crews are currently installing medians and curbs to better demarcate the parking zones from the bike lanes, and installation of permanent signage is ongoing.
Weather permitting, construction in this area is expected to be completed before the end of the year.
Project Update September 2025
Construction on the Seventh Street Active Transportation Network Plan (ATNP) – Year 1 project is starting September 2025. Crews will begin with preliminary mobilization and traffic control setup along Seventh Street between Agnes Street and Belmont Street. A permanent change to a one-way northbound traffic pattern from Queens to Fifth Avenue will be implemented, and residents can expect temporary traffic disruptions during construction.
Please follow posted signage and detours throughout the work period. We appreciate your support and cooperation during construction and apologize for any inconvenience this may cause.
What's Next?
-
Intersection upgrades: Completion of curb, sidewalk, and pavement work at Seventh Street and Belmont Street.
-
Signage installation: Ongoing installation of wayfinding, parking, and cycling signage.
-
Final clean-up: Site tidy-up and demobilization in December, weather permitting.
Traffic Impacts
Duration: September 22nd to December 2025
Hours of work: 7:00am to 5:00pm, Monday to FridayDuring construction, residents and visitors can expect:
- Temporary lane closures and detours
- Limited on-street parking availability
- Adjusted pedestrian and cycling routes
- On-site traffic control personnel
Expect delays and please follow all posted signage and detours.
We appreciate your patience and cooperation as we deliver these important upgrades.
Garbage and recycling collection will continue as scheduled. Access to homes and businesses will be maintained.
Contact
For more information please contact Erika Pollmuler, project manager, at or visit the Projects on the Go page.
Rotary Crosstown Greenway (5th - 8th Street)
Anticipated completion: January 2026Project Update
November 10, 2025
Thank you to residents for your patience over the weekend while crews placed concrete for sidewalks, curbs, and driveways along the south side of Seventh Avenue. The weekend work was necessary to recover time lost due to rain in previous weeks. Weather permitting, crews will complete the remaining concrete installation along the south side of Seventh Avenue between Fifth Street and Eighth Street early this week. During this time, paving of the new bike lanes on the south side of the street will also take place which will end the cycling detour on Hamilton.
During construction, there have been some delayed or missed waste collections in the area. Strata and multi-family buildings are asked to report these issues directly to their waste collection provider so they can propose an alternative collection method, such as a bin pull-out. Single family homes with missed collections should report this directly to the city through the web portal: Report Missed Collection
Construction crews remain on site to assist waste collection drivers as needed. Traffic control personnel are available to direct traffic, act as spotters, and temporarily move barriers to help facilitate access for collection vehicles.
September 26, 2025
The City would like to thank the residents and strata councils who reached out with their concerns during construction on the Rotary Crosstown Greenway East Project. In response, measures have been put in place to address wrong-way traffic, pedestrian safety, and waste collection. Our team has coordinated with the waste collection provider and the on-site contractor to implement the requested adjustments, including gravel improvements at driveways and support from on-site Traffic Control Persons. Waste collection service will return to its regular schedule within the next few collections.
The contractor has also increased signage, improved pedestrian barriers, and is working to expedite the installation of new sidewalks to permanently restore access. Cyclists are asked to follow the posted detour along Hamilton Street. We appreciate the community’s patience with the temporary pedestrian, cyclist, and vehicle detours while this important work is completed, a critical final step after many years of disruptions on Seventh Avenue.
Project Details
The City of New Westminster is enhancing the Rotary Crosstown Greenway along Seventh Avenue between Fifth and Eighth Streets to provide a safer, more comfortable, and attractive route for people of all ages and abilities to walk, bike, and roll.
As part of this work, the corridor will be upgraded with protected bike lanes, improved pedestrian crossings, new landscaping, and refreshed road surfaces. A mid-block raised crosswalk between Sixth and Eighth Streets will increase safety and visibility for pedestrians. The design reflects feedback gathered through public engagement and supports the City's broader goals for active transportation and accessibility.
Construction is now underway and will be completed in phases to minimize disruption.

Project Timeline
Project Update September 2025
Construction on the Rotary Crosstown Greenway is now underway. Crews have begun removals and replacement of the sidewalk, bike lane, curb, and road along the south side of Seventh Avenue from Eighth St to Fifth St. Ongoing infrastructure upgrades for local road storm drainage will cause mirror delays as crews trench in drainage pipes across Seventh Avenue. Access to residences and businesses remains open at all times with short closures during equipment moves and curb pours.
One way traffic is now in effect from Eighth St to Fifth Street, please abide be posted road signage. Cycling detour is in place from Moody Park to Hamilton Street, from Hamilton to Sixth Street, and from Sixth Street to Fifth Ave. Cycling specific detour signage is posted. If in doubt, the Traffic Control Personnel (TCP) are there to help!
Once the south sidewalk and bike lane are constructed, removals will begin on the North side of Seventh Ave.
Project Update July 2025
Construction on the Rotary Crosstown Greenway is now underway. Crews have begun preliminary mobilization and traffic control setup along Seventh Avenue between Fifth and Eighth Streets. Residents can expect traffic pattern changes and are encouraged to follow posted signage and detours.
What’s Next?
- Road paving: Crews are working toward paving the full road surface along Seventh Avenue by the end of November. This will include the intersection at Seventh Avenue and Sixth Street, and curb to curb from Eighth Street to Fifth Street. Expect some traffic impacts—please follow posted construction signage and direction from the on-site traffic control team.
- Sidewalk and driveway work: Replacement of sidewalks and driveways along the north side of Seventh Avenue will begin in mid to late November.
- Restoration: Topsoil placement, seeding, and planting are scheduled to begin at the end of November.
Traffic Impacts
During construction, residents and visitors can expect:
- Temporary lane closures on Seventh Avenue
- On-street parking restrictions
- Adjusted cycling and pedestrian routes
- Active traffic control personnel to guide road users safely
Expect delays and please follow all posted signage.
We appreciate your cooperation and understanding as we deliver these important upgrades.Garbage and recycling services will continue as usual, and access to homes and businesses will be maintained.
Contact Information
For more information please contact Erika Pollmuller, Project Manager, at , or visit the Projects on the Go page.
West End Sewer Separation and Watermain Replacement Project
Paving on 16th St and 8th Ave starting Oct 6th to end of Nov (weather dependent)project Update
November 2025
Please be advised Sandpiper Contracting LLP is scheduled to start utility upgrades the week of November 17th, 2025, along Eleventh Street from Third Avenue to Sixth Avenue.
Duration: November 2025 - Spring 2026 (Weather dependent)
Impacted Roads:
Eleventh Street: Third Avenue to Sixth Avenue. Road will be closed in segments to local traffic only. Temporary property access restrictions, as well as parking will be impacted. Please obey “no parking” signs as they will be moved daily. Temporary sidewalk restrictions.
October 2025
Paving work on 16th Street (from Edinburgh Street to 6th Avenue) and on 8th Avenue (from 14th Street to 18th Street) is scheduled to commence on October 13, with completion anticipated by end of November, subject to weather conditions.
PROJECT DETAILS
The project will include sewer separation work, installing green infrastructure (rain gardens), and replacing water mains that are at the end of their service life and due for replacement. The water main and sanitary sewer replacement program is intended to renew our aging infrastructure and to improve quality and capacity where required.
Duration
April 2024 to Spring 2027 (weather dependent)
Hours of Work
Monday - Friday: 7:00 am - 7:00 pm
Saturdays: 9:00 am - 6:00 pmImpacted Roads
Sixth Avenue - 20th Street to 18th Street
Duration: Fall 2023 - Summer 202516th Street - Tenth Avenue to Fifth Avenue
Duration: Spring 2024 - Fall 202518th Street - Tenth Avenue to Sixth Avenue
Duration: Fall 2024 - Spring 202620th Street - Tenth Avenue to Sixth Avenue
Duration: Winter 2026 - Spring 2027For more information on this project, please contact Amir Aminpour, Project Manager, at 604-515-3796 or or
Metro Vancouver Royal Avenue Pump Station Upgrade
Spring 2024 - Spring 2026Kenaidan Construction will be performing Royal Avenue Pump Station upgrades for Metro Vancouver on Quayside Drive. A two-metre path will be kept open for the public along the existing pathway west of the pump station. Five parking spaces on Quayside Drive will be used for loading/unloading (6:00 am – 6:00 pm, Monday – Friday).

Project details can be found here.
The Pattullo Bridge is a key connection between the communities of Surrey and New Westminster. The new toll-free four-lane bridge will provide important improvements for everyone using the bridge, including people who are driving, cycling or walking, as well as communities on either side of the bridge.
Click to view latest traffic impacts
To learn more about his project, as well as upcoming construction activity, please visit: www.pattullobridgereplacement.ca
For construction information or concerns, please call the 24/7 Construction Information Line at 1-844-815-6149.
For general project information, please email the project team at: , or call 778-379-2481.
RCH Redevelopment Project
Phase two of the Royal Columbian Hospital redevelopment project is now underway.Phase two will include the construction of a new acute care tower, an underground parkade, a new main entrance, and a rooftop helipad. Some aging buildings will also be replaced along with site enhancements. Phase two construction is expected to be complete in early 2025.
Phase three of the redevelopment project will upgrade and expand areas in the existing Health Care Centre and Columbia Tower to support the beds and services added in phase two. Phase three is projected to start in 2023 and complete in 2026.
Construction hours are Monday to Friday, 7:00 am to 8:00 pm (except holidays) and Saturday, 9:00 am - 6:00 pm.
