Roadworks


Please click on the sections below to see if there is road work taking place in your neighbourhood.

  • Ewen Avenue

    Project Task

    Location

    Duration

    Impact

    The City of New Westminster Electrical Department, BC Hydro and Telus is planning to undertake infrastructure upgrades along Ewen Avenue resulting in scheduled power and service outages. Affected customers will be notified by telephone, email, and door hangers.

    Ewen Ave (Boundary to Hampton) TBA Road open to public use.  Potential on-street parking impacts.

    For more information, please visit www.newwestcity.ca/ewenavenue

    Ryall Park Tennis Court Rehabilitation

    Project Task Location Duration Impact

    Improved surfacing to accommodate tennis and pickleball, as well as new nets and fencing.

    Ryall Park Tennis Courts January 21 – April 15, 2019

    Single lane along Salter Street during construction and deliveries.

    The existing park will remain open and fully functional during most of construction; however, public access to the tennis courts and portion of the lower half of Ryall Park will be temporarily closed during construction.

     

  • Project Type Location Duration Impact
    Sewer Rehab Royal Avenue and Stewardson Way November 3rd, 2018 - November 9th, 2018 Reduction in travel lanes, temporary removal of street parking, temporary driveway access restrictions

     

  • No current updates.
  • Braid Street Watermain Replacement

    Project Task

    Location

    Duration

    Impact

    BNSF & CN Rail Trenchless Rail Crossing (Contingent on approval of alignment change) Braid St at the BNSF & CN Railway

    Approx 1 month starting February 11

    Night Work – Single lane Alternating Traffic

    Two lanes of traffic during the day with closures for pits

    CP Rail Trenchless Rail Crossing (Contingent on approval of alignment change) Braid St at the CP Railway

    Approx 1 month Starting March 4

    Night Work – Single lane Alternating Traffic

    Two lanes of traffic during the day with closures for pits

    Install Fibre Boxes, curb and sidewalk prep. Braid St, from Canfor to Vulcan Intermittent work Curb Lane Closures maintaining one lane of traffic in each direction
    Watermain Tie-in Work (Metro Vancouver) Major Street and Rousseau Street March 11th to March 31st.  This is a 24 hour a day closure.

    Major Street from Rousseau Street to the laneway west of Rousseau Street will be closed to all traffic.

    Rousseau Street at the intersection of Major Street will be Single Lane Alternating Traffic with flag persons for a couple of days

    Other major projects in the area include the redevelopment of Royal Columbia Hospital (RCH). News and updates from this project, including road closure information, can be found here.

  • No updates at this time. 
  • No updates at the moment.

     

  • No current updates.

  • No updates at the moment.

     

  • No updates at the moment.
  • No current updates
  • No updates at the moment.