West End Sewer Separation and Watermain Replacement Project
project Update
December 2025
Due to weather conditions, paving work on 16th Street (from Edinburgh Street to 6th Avenue) and on 8th Avenue (from 14th Street to 18th Street) is anticipated to be completed Spring 2026.
November 7th 2025
Please be advised Sandpiper Contracting LLP is scheduled to start utility upgrades the week of November 17th, 2025, along Eleventh Street from Third Avenue to Sixth Avenue.
Duration: November 2025 - Spring 2026 (Weather dependent)
Impacted Roads:
Eleventh Street: Third Avenue to Sixth Avenue. Road will be closed in segments to local traffic only. Temporary property access restrictions, as well as parking will be impacted. Please obey “no parking” signs as they will be moved daily. Temporary sidewalk restrictions.
PROJECT DETAILS
The project will include sewer separation work, installing green infrastructure (rain gardens), and replacing water mains that are at the end of their service life and due for replacement. The water main and sanitary sewer replacement program is intended to renew our aging infrastructure and to improve quality and capacity where required.
Duration
April 2024 to Spring 2027 (weather dependent)
Hours of Work
Monday - Friday: 7:00 am - 7:00 pm
Saturdays: 9:00 am - 6:00 pm
Impacted Roads
Sixth Avenue - 20th Street to 18th Street
Duration: Fall 2023 - Summer 2025
16th Street - Tenth Avenue to Fifth Avenue
Duration: Spring 2024 - Fall 2025
18th Street - Tenth Avenue to Sixth Avenue
Duration: Fall 2024 - Spring 2026
20th Street - Tenth Avenue to Sixth Avenue
Duration: Winter 2026 - Spring 2027
For more information on this project, please contact Amir Aminpour, Project Manager, at 604-515-3796 or or
