Capital Paving - Various Locations

PROJECT DETAILS

Duration
Ongoing through Spring 2026

Hours of Work
Monday - Friday: 7:00am - 7:00pm
Saturday: 9:00am - 6:00pm

IMPACTED ROADS:

  1. Richmond Street - East Columbia St to Cumberland St
    ETA: Top Lift - May 12th (weather dependent)
     
  2. East Columbia Street - Hoult St to Hume Park
    Duration: April 21st - May 1st (weather Dependent)
     
  3. Eight Avenue- 22nd St to 20th St
    Duration:TBD
     
  4. Quayside Drive - K de K Court to Stewardson Way
    Duration:TBD

COMPLETED ROADS:

  • Louellen Street - Third Ave to Fourth Ave
  • Blackberry Drive
  • Garfield Street
  • Jamieson Court - Richmond St west to the cul de sac
  • Tenth Avenue - Twelfth St to Tenth St
  • Twelfth Street - Tenth Ave to Edinburgh St
  • Cumberland Street - Richmond St to East Columbia St.
     

CONTACT

For more information, please contact Peter Tsoutsouras, Project Manager, at 604-636-4340 or .