12. Braid Street & Brunette Avenue (CP)

Primarily operated by: CP
Safety audit complete: Yes
Design complete: Yes
Construction status: TBD
Whistle cessation process: Step 2

Comments:

Due to traffic congestion and access issues along the corridor, cessation will not be possible until these issues can be addressed.  Solutions to these issues are being looked at in conjunction with possible major highway improvements as part of the future Brunette Interchange. The schedule for the Brunette Interchange has not yet been determined.

Upgrades to the crossing surface were undertaken in December 2018. The City is also working to complete the final phase of the Braid Street Greenway.

Information last updated: June 5, 2019

  • How do I get involved?
    The Railway Community Advisory Panel, comprised of members from the City, railway companies, and the community formally discuss issues such as whistle cessation. If you would like to attend a meeting or bring a delegation you can contact Legislative Services at 604.527.4523 or  

  •     
  • For more information, please contact:
    Roger Emanuels
    Manager of Design & Construction
    604.527.4540