Pattullo Bridge Replacement Project

Update: February 13, 2026

After 89 years of service, the Pattullo Bridge is now permanently closed to all vehicle traffic. All four lanes on the new stal̕əw̓asəm Bridge will be open to traffic beginning Feb. 14 at approximately 7 am.

The sidewalk on the Pattullo Bridge will remain open to pedestrians and cyclists until the morning of Feb. 17. Pedestrians and cyclists are asked to remain on the sidewalk.

Additional information for pedestrians and cyclists can be found at pattullobridgereplacement.ca/active-transportation

Bridge Access:

Starting February 14, the Columbia Street on-ramp will be closed. Access to the stal̕əw̓asəm Bridge will be maintained via McBride Boulevard (Bridge Connector) and the Royal Avenue on-ramp.

A local closure of Columbia Street between McBride Boulevard and Elliot Street for approximately four to six weeks – starting February 26

  • Drivers will be detoured to Royal Avenue or Front Street. Columbia Street between 6th and Elliot will remain open for local traffic and access to all businesses on Columbia Street and Front Street Mews will be maintained at all times.
  • Drivers wishing to access the stal̕əw̓asəm Bridge from East Columbia can use Front Street. For more information about traffic detours, visit the Project website at www.pattullobridgereplacement.ca

Update: January 27, 2026

Starting February 6 at 8:00 pm, the Pattullo Bridge and stal̕əw̓asəm Bridge will be closed for approximately one week. This full closure is required for crews to complete the connections to the roadways on either side of the new bridge.
 
More details can be found here.
 

January 21, 2026

Starting January 21, access to East Royal Avenue will be restricted from 3 p.m. to 6 p.m. Access for first responders, buses, pedestrians and cyclists will be maintained at East Royal. Residents can access Victoria Hill via Memorial Drive.

January 16, 2026

Traffic is being switched to the stal̕əw̓asəm (Riverview) Bridge in phases to allow for completion of the tie-ins to existing roadways on either side.
 
Starting at approximately 5 a.m. on Monday, January 19, the Royal Avenue on-ramp will be closed. The on-ramp closure will remain in effect 24 hours a day for crews to remove a portion of the retaining wall alongside Bridge Connector and advance construction of the new on-ramp, tie-ins, and Royal-Agnes multi-use path overpass.
 
Drivers will use the Columbia Street loop-ramp via McBride Boulevard to access the Pattullo Bridge (see the graphic on the right). Alternate routes will also be advised through road signage.
 
 

The Pattullo Bridge is a key connection between the communities of Surrey and New Westminster. The new toll-free four-lane bridge will provide important improvements for everyone using the bridge, including people who are driving, cycling or walking, as well as communities on either side of the bridge.

Click to view latest traffic impacts 

To learn more about his project, as well as upcoming construction activity, please visit: www.pattullobridgereplacement.ca

For construction information or concerns, please call the 24/7 Construction Information Line at 1-844-815-6149.

For general project information, please email the project team at: , or call 778-379-2481.


Pattullo Bridge Replacement Project Municipal Agreement

Date posted:February 13, 2026